SPE Drilling & Completion
Volume 23, Number 3, September 2008, pp. 275-283

SPE-105027-PA

Kikeh Batch Setting: Case Study

View full textPDF ( 909 KB )

DOI  More information 10.2118/105027-PA http://dx.doi.org/10.2118/105027-PA

Citation

  • Flannery C., and Choo, B. 2008. Kikeh Batch Setting: Case Study. SPE Drill & Compl  23 (3): 275-283. SPE-105027-PA.

Discipline Categories

  • 1 Drilling and Completions

Summary

The semisubmersible rig Ocean Rover was used by Murphy Sabah Oil Company to batch-set 23 wellheads in 4,350-ft-deep water with zero health, safety, and environment (HSE) incidents.

The batch-set team worked to maintain safety and performance and to overcome numerous logistical and operational challenges. Implementing lessons learned and development of recommended practices resulted in continuous improvement throughout the project.

The program was completed in 63 days. The average installation time for conductor and surface casing was 3.36 days from start to finish. Total materials used were 50,000 ft of casing, 3,060 tonnes of cement, and 78,000 bbl of 16.6 lbm/gal dynamic kill drilling (DKD) mud.

Introduction

Kikeh is 75 nautical miles off the west coast of Sabah, Malaysia, in the South China Sea (Fig. 1). Murphy is the operator of the field, which is Malaysia’s first deepwater development.

The seafloor arrangement consists of 24 wells in a circular pattern roughly 150 ft in diameter with 20-ft spacing (Fig. 2). A spar and semisubmersible tender assist rig will be mobilized to the batch-set location to finish the drilling and completion operation.

Commonly encountered hazards in the area include shallow water flows (SWFs) and hydrates. Bottom currents tend to be almost nonexistent and lead to visibility challenges. Surface currents have not been a factor.

In April 2005, all 24 well locations were marked with marker buoys. The buoys were positioned to form a 4-ft box around each location. Cement blocks (no steel) were used for clump weight, and a 10-ft rope tether held the flotation buoy to the block.

In May 2005, Slot 1 was drilled to provide additional geological data. This well provided important information regarding the upper soils and hazard confirmation, setting a benchmark for the remaining 23 wells to be batch set in April 2006.

Six of the 23 wells would have only the conductor installed. The remaining 17 wells would have both the conductor and surface casing installed (Fig. 3).

The Ocean Rover has worked for Murphy in Malaysia since July 2003 and has provided exceptional value. The rig is conventionally moored, and it has a single derrick, trip saver, large pump capacity, and 6,050-ton variable deck load. More importantly, the personnel onboard the Ocean Rover have consistently demonstrated a commitment to safety and a can-do attitude.

View full textPDF ( 909 KB )

History

  • Original manuscript received: 12 October 2006
  • Meeting paper published: 20 February 2007
  • Revised manuscript received: 20 August 2007
  • Manuscript approved: 12 February 2008
  • Version of record: 15 September 2008