Derisking a Heavy-Oil Development: A Case Study of the Bentley Field

Fig. 1—Bentley field depth-structure map showing well locations.

An appraisal program involving the Bentley field located on the UK continental shelf has addressed the key technical concerns associated with developing viscous crude in an offshore environment. The program demonstrates how sustainable commercial flow rates can be achieved through the selection of a suitable completion design—including a downhole electrical submersible pump (ESP) and a downhole diluent-injection strategy—and through keeping within an appropriate operating-pressure and -temperature envelope.

The Bentley Field

The Bentley field, located in Block 9/3b in 110 m of water, contains approximately 900 million STB in place of heavy (10 to 12 °API) viscous (1,500-cp) crude. The field exhibits four-way dip closed at the uppermost Palaeocene, lowermost Eocene, and Dornoch sandstone level and covers an area of approximately 16×5 km at a depth of approximately 1.1‑km true vertical depth subsea. The reservoir is high porosity (33%), with net-/gross-pay ratio of 90%, and with ultra­high apparent horizontal permeabilities approaching 50 darcies on the basis of flow-test measurements, but consistent with unconsolidated sand.

Following an extensive appraisal program, a development was planned of which 257 million STB of 2P reserves is estimated to be recovered over a 35-year production period. In addition, it is estimated that 48 million STB of 2C contingent resources could be extracted commercially beyond the end of the currently planned facility life.

This article, written by JPT Technology Editor Chris Carpenter, contains highlights of paper SPE 172858, “Derisking a Heavy-Oil Development—A Case Study of the Bentley Field, UKCS Block 9/3b,” by B.H. Brennan, SPE, C. Lucas-Clements, S. Kew, SPE, and P.F. Dempsey, SPE, Xcite Energy Resources, prepared for the 2014 SPE International Heavy Oil Conference and Exhibition, Kuwait City, Kuwait, 8–10 December. The paper has not been peer reviewed.
...
This article is reserved for SPE members and JPT subscribers.
If you would like to continue reading,
please Sign In, JOIN SPE or Subscribe to JPT

Derisking a Heavy-Oil Development: A Case Study of the Bentley Field

01 March 2015

Volume: 67 | Issue: 3

STAY CONNECTED

Don't miss out on the latest technology delivered to your email weekly.  Sign up for the JPT newsletter.  If you are not logged in, you will receive a confirmation email that you will need to click on to confirm you want to receive the newsletter.

 

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT

ADVERTISEMENT