Integrated Asset Modeling: An Approach to Long-Term Production Planning

Getty Images

With declining trends in production and dwindling reserves for a 35-year-old offshore field, the Samarang Redevelopment Project was initiated with a vision toward implementing integrated operations as an asset-management decision-support tool. To realize expected reserves and optimize the production, an integrated-asset-model (IAM) concept is introduced with state-of-the-art modeling techniques to treat the asset as a whole unit rather than as isolated silos, which had been the traditional approach.

Introduction

The Samarang field is located in Subblock 6S-18 northwest of Labuan in eastern Baram Delta province. The production history of the field, first discovered and developed in the 1970s, is discussed in detail in the complete paper.

A full-field review was carried out from 2004 to 2007 with the objective of identifying redevelopment opportunities. A field-development plan (FDP) was then established before an alliance was signed in 2010 to redevelop the field. The redevelopment team has drilled more than 17 infill wells, obtained new 3D-­seismic data, carried out several studies including fine tuning of the enhanced-oil-­recovery (EOR) development plan, and executed an extensive program of production enhancement and surveillance activities to boost the field production. This has given the team further insight into the Samarang field potential as well as the untapped near-field potential.

This article, written by JPT Technology Editor Chris Carpenter, contains highlights of paper SPE 176322, “Samarang Integrated Operations: Integrated Asset Modeling—An Innovative Approach for Long-Term Production Planning Focused on Enhanced Oil Recovery,” by W. Sifuentes and J. Moreno,Schlumberger; P. Kumaran and R. Hamdan, Petronas; M. Muhamed Salim, M. Mohd. Som, H.W. Lee, A. Ahmad, N. Pangereyeva, S.S. Biniwale, N.J. Rodriguez, J.T. Nitura, R. Alia, O.A. Talabi, and V. Halabe, Schlumberger; and S. Pedraza, SPE, prepared for the 2015 SPE Asia Pacific Oil and Gas Conference and Exhibition, Bali, Indonesia, 20–22 October. The paper has not been peer reviewed.
...
This article is reserved for SPE members and JPT subscribers.
If you would like to continue reading,
please Sign In, JOIN SPE or Subscribe to JPT

Integrated Asset Modeling: An Approach to Long-Term Production Planning

27 November 2016

Volume: 68 | Issue: 12

STAY CONNECTED

Don't miss the latest content delivered to your email box weekly. Sign up for the JPT newsletter.