How Ready Is Your Project for Delivering Production?

In recent years, projects in upstream oil and gas have become more complex, remotely located, and, therefore, costly and difficult to deliver.

ogf-2012-04-culturehero.jpg
Source: Getty Images.

In recent years, projects in upstream oil and gas have become more complex, remotely located, and, therefore, costly and difficult to deliver. Research shows that one of the key performance indicators—attainment of production as per the basis of design—is not achieved without significant further investment and significant delay (Merrow 2011). The findings are an industrywide phenomenon. Oil and gas companies have started to think about how to reduce the risk of costly remedial actions to meet original production targets.

There are principally two activities that companies employ to optimize internal processes for better outcomes: (1) strengthening project assurance activities and (2) planning ahead for long-term operations. Recent experience in coal seam gas (CSG) to liquefied natural gas (LNG) projects on the east coast of Australia further enforces these principles.

1. Value assurance fostering system integration

After the late 1990s trend to return to the roots of the E&P sector, after a period of diversification into other businesses, capital discipline was instituted in most large multinational oil and gas companies. The value assurance framework was principally employed to enhance the efficiency of capital invested by offering “more bang for the buck.”

Because of the natural movement of employees and increased pressure from shareholders, capital allocation discipline and value assurance have found widespread application in the industry. Over the years, the same framework expanded to include technical and operational requirements that stipulate minimum standards for deliverables at various stages of project delivery such as concept selection, detailed design, construction, and commissioning.

A key learning in applying these processes was to recognize the large degree of systems interaction that require higher levels of integration. The model developed by Shenhar and Dvir (2007) classifies projects by a number of key variables and attributes certain factors to overcome factors such as uncertainty, complexity, organizational knowledge, and urgency. These factors correlate with the observations in Merrow’s analysis of executed megaprojects (Merrow 2011).

In identifying the key drivers for each project, a different approach, team composition, and organizational setup is required. A good example is the difference between a repeat project rolling out an existing widget in another location to a crisis management project as a response to a natural disaster or an external threat. The sponsors, available resources, and expectations of the two projects will be very different, thus leading to very different approaches and outcomes.

In general, the more complex the project, the higher the level of integration required to achieve project objectives. The lower the level of integration, the more likely that project objectives such as production attainment, budget, or schedule are not achieved.

Some examples of the booming CSG to LNG business are

Subsurface reality with surface facility integration

An adequate appraisal campaign is required to reduce uncertainty as far as economically feasible in terms of well fluid composition and production profiles. For example, the presence of solids will require a different surface facility solution if the solids cannot be contained by an appropriate and cost-efficient well completions strategy.

In large-scale CSG developments, the need to standardize equipment to reduce costs has to be offset with the range of potential subsurface outcomes. An early view on long-term operation and maintenance philosophies is also essential in designing an optimized field development plan with a target availability for equipment. Inadequate design can lead to bottlenecks, for example, in gas-locked well gathering systems at high points in the terrain where no provisions for venting mechanisms are in place.

Optionality for the application of new technologies, land access constraints, and other external factors (e.g., carbon taxation) should be addressed in the early stages of project development when changes are less costly to implement. A potential approach is to prototype equipment and installation early to be able to standardize rapidly for projects with replication potential such as wellhead skids.

Enabling infrastructure integration, including permits and licensing

Greenfield sites requiring accommodation, road, electrical, and water infrastructure

Many megaprojects are executed in greenfield areas with little or no infrastructure. The challenge is to ensure that the project team addresses infrastructure requirements with the same diligence and rigor as is applied to the cash generating the oil and gas asset. Neglecting access, accommodation, power and water supply, or disposal until later in the engineering definition process will more than likely lead to costly retrofits at a later stage.

Permits and licensing requirements

Understanding the legislative requirements and permitting processes in detail is crucial for the owner’s team to build a robust schedule and project cost estimate. Furthermore, the processing capacity and experience of the government agencies have to be taken into consideration. In some locations, there is no effective legislative framework covering oil and gas production in place.

Upstream facilities integration

Control system within facilities and across multiple sites

Megaproject facility control system implementations are typically large scale and geographically widespread. Commercial realities and technical capabilities often dictate a multivendor approach to automation driving various interfaces requiring a detailed system integration between in-field measuring devices (supervisory control and data acquisition), control systems, and proprietary package control systems for specialized equipment such as gas compressors. Shortfalls in interface engineering often do not present until the commissioning and operating phase, when systems have to work together. Costs for rectification become material while production and commercial losses accumulate rapidly.

Vendor-designed systems within engineered systems

System integration is key in megaprojects. Given the nature of the delivery structure, different project teams build separate pieces of the overall project scope. Integration between these teams is often very limited as reflected in a number of high-level interface documents usually authored very early in the project.

Individual project teams underestimate the overall complexity of the complete project scope and an overall integrating function is often missed. Processes such as a flawless startup and verification of readiness integrate engineering, commissioning, construction, and business requirements before startup. Many of the incipient issues in startup and early operations, however, result from an incomplete integration during the engineering definition process.

2. Instituting operations readiness to inject practicality and long-term viability into projects

  • Front-end loading
    • Obtain lessons from previous company projects, contractors, or industry lessons.
    • Involve operations in design process earlier to achieve operable design. Availability of experienced operations personnel early in the design process can be an issue in remote greenfield locations or new plays such as unconventional oil and gas. This can be to the detriment of long-term operations in which the absence of operating experience in design presents a risk of oversight on genuine process and personnel hazards and high costs in operations.
  • Recruitment and onboarding
    • Recruit in advance and build capability and systems across operations and maintenance. Aside from the ability to influence design, early recruitment of operations and maintenance teams derisks facility startup and early operations by ensuring that the processes, procedures, and tools for operating facilities are established ahead of the introduction of hydrocarbons. Success of the preoperation phase hinges on the depth and breadth of the available skill pool and the amount of available funding.
  • Training and competency
    • Involve operators in authoring and reviewing operating procedures, training, and competency assessments. Competition for operations resources in a constrained oil and gas labor market has presented CSG companies in Queensland, Australia, with a significant challenge in building a competent workforce. Early hire of large numbers of nonproduction trades into hydrocarbon operator roles increases the emphasis on building effective training and competency systems. Specialist skills such as high-voltage network operations also need to be brought in to support critical support functions.
  • Maintenance build and spares
    • Provide a capable and flexible maintenance system early. Include asset integrity thinking early such as major accident hazards and safety critical elements.
    • Optimize before first operation through integrated planning.
  • Continuous improvement (lessons and assurance)
    • Build an organization that learns internally to improve the delivery on project and shares lessons across multifunctional groups at the corporate level. Successful CSG/LNG project implementation requires diligence across each phase of execution from prefeed to operations. Formal “gate” reviews by subject matter experts, measured against key success criteria before the end of each project phase, offer opportunities to identify gaps in facilities and business readiness to operate. Subsequent learnings from the initial operation of early facilities allow the “design out” of issues in subsequent stages, thus building a momentum in delivery efficiency in an execution program.

Conclusion

Value assurance and operations readiness are two key factors that lead to better project outcomes. These findings are underpinned in research. There are a number of steps that will pay off in the long run in any project, with the most pertinent being

  • Building operational capability early and engaging with the project
  • Integrating between designers, vendors, and owners
  • Ensuring that the right skills are available in the company’s workforce
  • Building a learning organization

References

Merrow, E.W. 2011. Industrial Megaprojects: Concepts, Strategies, and Practices for Success, first edition. John Wiley & Sons.

Shenhar, A.J. and Dvir, D. 2007. Reinventing Project Management: The Diamond Approach to Successful Growth and Innovation, first edition. Harvard Business School Press.

Acknowledgment

The authors would like to thank the QCLNG Integrated Completions Group for supporting the publication of this paper, and in particular, Paul Meech and Craig Hales for their personal leadership and guidance.

Kai C. Eberspaecher, SPE, is a senior associate at Advisian. Before joining the company, he worked for 10 years at BG Group and was the upstream operations readiness manager of the Queensland Curtis Liquefied Natural Gas (QCLNG) project. Eberspaecher is a fellow of the Institute of Chemical Engineering, a chartered engineer in the UK and Europe, and a registered professional engineer in Queensland. He holds an MEng in chemical engineering from Imperial College London and an MBA from the Tepper School of Business at Carnegie Mellon University.

Jamie W. Gabb is the integrated startup operations manager of BG Group’s upstream facilities of the QCLNG project. Before joining the company, he worked for 16 years in a variety of operations, engineering project, maintenance, and asset management roles in the electric utility sector in Australia and Europe. Gabb is a member of the Institute of Engineers Australia and a registered professional engineer in Queensland. He holds an MEngSc from Queensland University of Technology and a bachelor’s degree in electrical and electronic engineering with honors from the University of Queensland.