Minimizing HSE Impacts During Design and Construction of a Major Gas Pipeline Through the Baltic Sea

During the design of two parallel gas pipelines from Russia to Germany through the Baltic Sea, major design changes were made to minimize project impacts, resulting in rapid approval by all five affected countries.

Oil and Gas Facilities logo on abstract background

Summary

From 2010 to 2012, two parallel gas pipelines (the Nord Stream Project) were installed in the Baltic Sea between Vyborg in Russia and Greifswald in Germany. The pipeline system will enable an annual transport of 55 billion m3 (bcm) of natural gas from the large Russian gas fields to the European gas grid.

Comprehensive environmental and safety studies were carried out in the design phase. The outcome of these studies was used in iterations with the pipeline-design process, ensuring that the final pipeline design has minimal impact on the environment as well as on human activities in the Baltic Sea. Also, due consideration has been given to ensuring the health and safety of construc­tion personnel and minimizing the environmental impacts during construction.

Major changes to the design were made in order to minimize project impacts, including

  • An originally planned intermediate service platform was “engineered out,” eliminating the risk of ship collisions in the operation phase.
  • The pipeline route was optimized to avoid sensitive natural areas and heavily used ship-traffic routes.
  • Extensive geophysical surveys were carried out in order to identify and mitigate interaction with dumped chemical and conventional munitions and cultural-heritage objects.
  • It was ensured by theoretical analysis verified by measurements that the pipeline with the chosen route did not have a negative impact on inflow and mixing of water in the Baltic Sea.
  • Environmental monitoring and subsequent feedback to the construction vessels were carried out during seabed-intervention works near sensitive habitats.

Unique for this project are the major design changes that have taken place as a result of the health, safety, and environment (HSE) analysis. One outcome of this has been that all five affected countries have given permit to the project in a relatively short time period, even though it is the first major pipeline project in the Baltic Sea. 

Read or download the full SPE paper 145390-PA.