AkerBP’s Valhall Flank West Development Progresses

Topics

This week the Valhall Flank West topsides was moved outside at the Kvaerner Verdal yard. The crane and helideck have been installed. First oil is slated for late 2019.

In January 2017, the Valhall and Hod fields in the southern Norwegian North Sea surpassed 1 billion BOE produced, which is more than three times the volume expected at the opening of the field in 1982. Another 500 million bbl is aimed for as production continues.

Valhall comprises a field center with six platforms and two unmanned flank platforms. The field is located in 70 m of water. Hod is tied back and remotely operated from Valhall.

The field was originally developed with three facilities for accommodation, drilling, and processing. The Valhall complex today includes six separate steel platforms for living quarters, drilling, wellheads, production, water injection, combined process- and hotel platform, respectively. These platforms are bridge-connected.

The Valhall Flank developments are two identical unmanned wellhead platforms each equipped with 16 drilling slots and located about 6 km (one to the north and one to the south) from the existing Valhall facilities where wellstreams are processed. The South Flank started production in 2003 and the North Flank came on stream in 2004.

Liquids are routed via pipeline to Ekofisk and further to Teesside in the UK. Gas is sent via Norpipe to Emden in Germany.
 

 

ADVERTISEMENT


STAY CONNECTED

Don't miss out on the latest technology delivered to your email every two weeks.  Sign up for the OGF newsletter.  If you are not logged in, you will receive a confirmation email that you will need to click on to confirm you want to receive the newsletter.

 

ADVERTISEMENT


MOST POPULAR

ADVERTISEMENT


EXPLORE ARTICLES BY TOPIC

ADVERTISEMENT